| Scheme participant | Pormpuraaw Aboriginal Shire Council |
---|
| Eligible offsets project name | Raak Nguunge |
---|
| Project ID | EOP100813 |
---|
| Contract ID | |
---|
| Contracted on | December 2018 |
---|
| Method | Carbon Credits (Carbon Farming Initiative - Emissions Abatement through Savanna Fire Management) Methodology Determination 2015 |
---|
| Method URL | https://www.legislation.gov.au/Details/F2015L00344 |
---|
| Method type | Savanna Burning |
---|
| Project description | This project involves strategic and planned burning of savanna areas in the high rainfall zone during the early dry season to reduce the risk of late dry season wild fires. |
---|
| Date Project Registered | 14 October 2014 |
---|
| Project location | Queensland |
---|
| Project location (postcode) | 4871 |
---|
| Project Area(s), where the project is an area based offsets project | 6/SP241276, 5/SP241276
This project is in the Pormpuraaw local government area. |
---|
| Mapping file URL | http://www.cleanenergyregulator.gov.au/DocumentAssets/Documents/ERF-Mapping-Files/EOP100813.kml |
---|
| If the area-based project is covered by a regional natural resource management plan, is it consistent with that plan? | Yes |
---|
| Joint Implementation project | No |
---|
| Is the project area or project areas subject to a Carbon Maintenance Obligation (CMO)? | n/a |
---|
| Conditional upon all regulatory approvals being obtained | No |
---|
| Conditional upon the written consent of relevant interest holders | No |
---|
| Nominated Permanence Period, if applicable | n/a |
---|
| Finish date of permanence period, if applicable | n/a |
---|
| Notes | 02/02/2016 Variation of project method - from the Carbon Credits (Carbon Farming Initiative) (Reduction of Greenhouse Gas Emissions through Early Dry Season Savanna Burning - 1.1) Methodology Determination 2013 to the Carbon Credits (Carbon Farming Initiative - Emissions Abatement through Savanna Fire Management) Methodology Determination 2015.
06/08/2018 This project was contracted in Apr-15 and CAC139389 has now been completed. |
---|
| ACCUs Total units issued | 93,387 |
---|
| KACCUs Total units issued | 93,387 |
---|
| KACCUs Units Issued in Financial Year 2012/13 | 0 |
---|
| KACCUs Units Issued in Financial Year 2013/14 | 0 |
---|
| KACCUs Units Issued in Financial Year 2014/15 | 9,790 |
---|
| KACCUs Units Issued in Financial Year 2015/16 | 16,889 |
---|
| KACCUs Units Issued in Financial Year 2016/17 | 13,769 |
---|
| KACCUs Units Issued in Financial Year 2017/18 | 24,545 |
---|
| KACCUs Units Issued in Financial Year 2018/19 | 10,881 |
---|
| KACCUs Units Issued in Financial Year 2019/20 | 17,513 |
---|
| Name of person/s to whom the KACCUs issued | Pormpuraaw Aboriginal Shire Council |
---|
| Total Number of KACCUs units relinquished | 0 |
---|
| NKACCUs Total units issued | 0 |
---|
| NKACCUs Units Issued in Financial Year 2012/13 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2013/14 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2014/15 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2015/16 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2016/17 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2017/18 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2018/19 | 0 |
---|
| NKACCUs Units Issued in Financial Year 2019/20 | 0 |
---|
| Name of person/s to whom the NKACCUs issued | n/a |
---|
| Total Number of NKACCUs units relinquished | 0 |
---|